Activity Plan

Indicative construction sequence (all dates tbc.):

  • Spring/Summer 2025 - Three Mills Lane works
  • Summer 2025 - Hancock Road works
  • Autumn 2025 - Imperial Street works
  • Spring 2025 - Autumn 2025 - Lighting, wayfinding and potentially CCTV
  • Autumn 2025 - Street tree planting

To keep in touch with the project or provide your view on the proposals, please get in touch via the contact details below:

connectivityportfolio@londonlegacy.co.uk


Links to planning documents:

LLDC Local Plan 2020-2036

Bromley-by-Bow SPD (2017)