Construction works ongoing!

The project is now under construction with works ongoing on site, see outline timetable below:

June 2025 - Construction starts on site for early phases.

June 2025-September 2025 - Works complete to ramp adjacent to Montfichet Road

September 2025-December 2025 - Works ongoing to Pool Street southern arm

October 2025-November 2025 - Parallel UCL East utility connection works underway (not part of this project)

Spring 2026 - Works to remaining section of Pool Street

Summer 2026 - Works to Montfichet Road/Pool Street junction

Autumn 2026 - Works to Pool Street/Carpenters Road junction